Road Construction Update

Highway 66 Widening Project-Phase III (TDOT Project)

Estimated completion date: December 31, 2015. The project started in February 2012 and was awarded to Simpson Construction Company in the amount of $32,517,493.62. The entire project from I-40 to downtown Sevierville will widen the existing highway from 4-lanes to 6-lanes, improving congestion and enhancing safety for the traveling public. For additional project information on Phase III, visit http://www.tdot.state.tn.us/highway66/ or contact TDOT project contractor Amec Foster Wheeler at 865-429-4509.

Hwy 66 Phase III Bridge Work
Phase III Bridge Widening.
Photo courtesy of Amec Foster Wheeler.

Diverging Diamond Project and Associated Exit 407 Improvements (TDOT Project)

The new interchange opened June 30, 2015, more than two weeks ahead of the projected July 14 opening date. The project started in March 2104 and was awarded to J & M Grading Division LLC in the amount of $15,647,551.60. The work consisted of grading, drainage, rehabilitation of a concrete cast-in-place bridge, and paving on I-40 at the State Route 66 interchange (Exit 407). Bridge traffic has been reconfigured into a diverging diamond pattern to enhance traffic flow and improve efficiency on Highway 66 and the I-40 Exit 407 ramps. Some work remains, including opening all lanes on the eastbound and westbound off ramps and additional paving and road markings.

 DD Opening morning